Planning Parallel Activities on Same Resource

Eheh, I know. Unfortunately there are a mess of possible planning criteria (that's why project mgmt is fantastic!!). Mine was just an idea; let'...

12 years ago
Reply
Planning Parallel Activities on Same Resource

Hi Babynus, protion, all. First of all, is not a bug, nor a mis-configuration or whatever, just a behavior (proving how good is this tool). I got ...

12 years ago
Reply
Planning Parallel Activities on Same Resource

:(:(:( Consider my project includes more then 800 activities ... very difficult to debug Here another screenshot: I will try to reproduce t...

12 years ago
Reply
Planning Parallel Activities on Same Resource

Babynus, I re-created the DB and re-insert all the activities to have a clean situation. Problem arise again. I notice that it happens in this ...

12 years ago
Reply
Planning Parallel Activities on Same Resource

Hi Babynus, none of listed causes fits my case. - None of the projects is set as "fix planning" - ALL projects are OPE - No real work yet (I'm i...

12 years ago
Reply
Planning Parallel Activities on Same Resource

Yes, it should 🙁 Maybe I got the point. Looking at the picture attached taken from my plan, planned with ASAP, seems dependencies have not been ta...

12 years ago
Reply
Planning Parallel Activities on Same Resource

Hi Babynus, very fast reply!!! I set work for all the elementary activities but ASAP still didn't consider the dependencies, that's why I used fixe...

12 years ago
Topic
Replies: 15
Views: 12511