Hi Phil, below the standard access modes: Change here, where the arrow ends. Regards, Klaus
Hi Pierre, may be you have a lock at Checklists - this might be a good workaround. Regards, Klaus
Hi Julius, did you assign activity to the user which should see the activity? This is prerequisite 1. Access rights should be accordingly allow to...
Hi Phil, may I suggest to do following: see values in Access rights - Access to data (project related). For External team member should set adequat...
Hi Phil, not clear if I understood you right. In the line 'progress' there will be no line with work. It shows percentage of progress. Work is ...
Oh, I see. It tried to increase font size in Options- using FF- , but there was no effect on ProjeQtor. With zoom it still works and as workaround ...
Give a try to reports in 'real work'. There are yearly reports.
... and what's about`:: Report - Planning - Monthly planning resource/project/activity
Hi Chris, in the menu, go to reports - real work - e. g. 'Detailed work per resource - monthly' Regards, Klaus
Hi Chris, did you try the reports? Regards, Klaus
I thought about and have following insights: . If a mail sender is not in contacts, then he could not be selected to be a issuer or requester. I...
I would define a 'dummy' project to which these Tickets / Actions should be assigned. Then somebody has to assign it manually to a project - depending...
Hi llapierre, I used it several year in the way, to collect requests and assign them to dedicated releases. This worked well in a semi agile approa...
What you describe sounds like it works in MS Project. I didn't find this flexible way to lift and shift resource allocations. But an proper resource a...