The Version I am using is 3.1.1. I have not reproduced it yet. The version being used is standard. No code has been changed.
OK so the resource need not be at the top level. Please can the selection be made from the level above?
No dependencies between tasks A resource was assigned to tasks and had no time left This was the reason that using a higher priority should have...
I do disconnect and reconnect. What I need is to only be allowed to select resources from the project in the level above as this is the control th...
thank you for the reply. However I do not want something to act as Soon As Possible when I add times to the users. If I did then I would use As Soon...
This is my example Project 1 => Project 2 Project 2 is a sub project of Project 1. Unless I put the Resource A into Project 1 then the Reso...