Last seen: 7 Mar PM 15:033
Oups, I think I need some hollidays, sorry for the mistake and thank you very much.
Thanks. In the resource planning, when I click on the calculate icon, a configuration window pops-up to choose the project and the start date. In t...
Hi, done, but the problem remains unsolved. I have switched the GUI in english to be sure to uncheck the right option.
Hi, I think both are usefull. In my company, I have to communicate planned workload per resource until end of project. This is ajusted every week. An ...
In the workload report provided, the 4th line "Dev" is a pool of resources. The second screenshot shows the resources of this pool. My interrest is fo...
This is actually a workload report. Enclosed a view of the report, and the definition of the pool "Dev". There are two lines in the workload report f...
Thanks, so will delete accounts and check "is a user" for resources. For existing projects, it would be nice to be able to fusion resources having th...
Hi, There is one François created as a resource first to perform assignment to activities, then later an account has been created for this François...