Hello, I reproduced my example in the demo, "Manager" section. The project is called TEST_"Total expenses and costs per month" report. It includ...
What do you mean by saying "could you please try and reproduce the case on Demo" ?
I've found the origin of the problem but still didn't solved it. The 114 450.15€ calculated by the "Total expenses and costs per month" report was ...
Hello, The version I'm working with is the 11.4.4. The difference doesn’t come from the « activity expenses » as I’ve verified all the numbers i...
Hello, Is there a possibility to create this kind of report today ? JL
Hello, I'll give you a list (but I'm not sure I've got them all) : - "Total dépenses et coûts par mois" - "Dépenses totales par mois" - "Tableau...
Indeed it was an access problem, solved with my IT manager. Thank you for your answers.
But I don't find it, that's the problem... maybe I don't have access to it. I'm gonna ask my IT manager. Thank's for your answers.
Thank you. But is there any menu where you can access and modify all the recipients ? And if yes, where could I find it ?
Hello, You're right, the periode had been validated with the timesheet validation. Thank you for your answer, I'm still learning ! J.L.