Eheh, I know. Unfortunately there are a mess of possible planning criteria (that's why project mgmt is fantastic!!). Mine was just an idea; let'...
Hi Babynus, protion, all. First of all, is not a bug, nor a mis-configuration or whatever, just a behavior (proving how good is this tool). I got ...
:(:(:( Consider my project includes more then 800 activities ... very difficult to debug Here another screenshot: I will try to reproduce t...
Babynus, I re-created the DB and re-insert all the activities to have a clean situation. Problem arise again. I notice that it happens in this ...
Hi Babynus, none of listed causes fits my case. - None of the projects is set as "fix planning" - ALL projects are OPE - No real work yet (I'm i...
Yes, it should 🙁 Maybe I got the point. Looking at the picture attached taken from my plan, planned with ASAP, seems dependencies have not been ta...
Hi Babynus, very fast reply!!! I set work for all the elementary activities but ASAP still didn't consider the dependencies, that's why I used fixe...