About "meeting" : how to assign more working time than ETQ

4 Posts
2 Users
0 Reactions
2,844 Views
(@noisette)
Posts: 24
Active Member
Topic starter
 
[#3978]

Hello
I asked again a question about meeting's assignation.
I would like to force planning to accept that for a meeting someone could work more than the 7 hours (ETQ).
If I have a meeting with 8 hours... the assigned resource has always 1 hours not planed, because it is more that the official duration of working time for this resource (ETQ = 7 hours).
Is it possible to force it ?

Best regards
Christophe


 
Posted : 28 Dec 2016 17H26
(@babynus)
Posts: 14952
Member Admin
 

Is it possible to force it ?

No


 
Posted : 28 Dec 2016 17H33
(@noisette)
Posts: 24
Active Member
Topic starter
 

Is it possible to force it ?

No

Really? you can't assign for one exceptional day more that 7 hours (if ETQ = 7 hours) ? Never... Even for a meeting?
It is strange... no?
We have part-time worker... 0?8 ETQ. And all the meetings are more or less 7 hours. And the resources need to travel, and this time is for our organisation "50% working time". So for a 7 hours, the 0?8ETQ could spend 12 hours for the meeting. How could I plan a such extra times?
Don't you think it could be a good thing to make it possible in a new version?
Christophe


 
Posted : 28 Dec 2016 19H36
(@babynus)
Posts: 14952
Member Admin
 

Really? you can't assign for one exceptional day more that 7 hours (if ETQ = 7 hours) ? Never... Even for a meeting?

No, not for resource with capacity = 1
Planning will never plan more than resource capacity.

So for a 7 hours, the 0?8ETQ could spend 12 hours for the meeting. How could I plan a such extra times?

You cannot plan this extra time on same day for the meeting.
Only possibility is to directly enter real work for the meeting : real work has not constraint and is always right.

Don't you think it could be a good thing to make it possible in a new version?

No, this is one basis on Planning calculation in ProjeQtOr...


 