Hello,
How does ProjeQtOr order the activities when planning ?
First I had thought by "priority" then by "WBS", but it seems to me the "id" (that is, the order of creation of the activity) is also taken into account (not sure) ? Predecessors and successors must also be taken into account.
I have some doubts : can you tell me which elements are taken into account and in which order ?
(Sorry for the question, but I did not find the documentation about it)
Thank you !
1) Dependencies (predecessor-successor)
2) Planning mode (Meetings and Regular between dates first)
3) Project priority
4) Activity priority
5) WBS
Id is not taken into account.