Hello eveyone,
I'm using Projector ver 12.3.3.
Here's my question,
When activities are imported (no error), tasks (mean lines in activities) are not linked to each other. I assume "originId" is should be used for the purpose I want
below the table import via activity. No other tables are imported.
In the example below, I expect ID 646 linked to 645, id 647 linked to 646, and ID 648 linked to 647.
Can you help to achieve my request?
In advance, thank you very much to the community.
JeremyidreferencenametagsidActivityTypeidProjectexternalReferencecreationDatelastUpdateDateTimeidUseridContactoriginTypeoriginIddescriptionidActivityidStatus645II - Domaine 2622 2026-01-30 1 645Domaine Intelligence Artificielle de la PSSI 1646I.AI.A -sub domain 2622 2026-01-30 1 645Cadre de gouvernance et d’usage de l’IA 1647I.A.05I.A.05 - sub domain 2622 2026-01-30 1 646Politique d’usage et de contrôle de l’IA 1648I.A.05.10I.A.05.10 - branch 2622 2026-01-30 1 647Définition des cas d’usage IA autorisés et interdits 1
Hello,
OriginId corresponds to the plus button above the description.
Export an activity from your activity board in csv format and you will see how to import data.
NB: when you insert tables, please take a screenshot or attach the file, otherwise it will be unreadable.
Have a nice day,
When you say "linked" you mean dependencies ? The lines appearing in the planning ?
If so, this is not possible to import directly on Activities through import.
Only possibility to import dependencies is to use Project Import plugin.