Hello,
I have created an administrative project (see below) with some activities :
I put :
- A validated starting date (the same for the project and its activities) -- 01/01/2019
- A validated end date (the same for the project and its activities) --12/31/2019
I have two issues :
- I am always asked to plan the project however it's an administrative one and the automatic planning feature is activated
- When I make some imputations on the activities, the status of the project changes itself, however the activities' status don't change
Thank you in advance for your return.
Best regards
Hello,
what is your version of projeqtor ?
If your not in the lasted version try to update.
hello
Administrative projects typped ADM can not be planned. They allow to inform all absences. You must type your project with "operationnal" type OPE, configuration that has been done beforehand by your administrator.
OPE type projects are planned taking into account the data provided on the ADM Projects to give work day by day ( depending on also the mode of planification choosen) when resource are able to work in the futur.
I invite you to read the user guide before you start.
Regards.
Hello,
I have created other administrative projects with their activities. I made the tests with versions 7.4.4 and 8.0.3. I don't have the status problem anymore. But I still have the message saying that I need to plan. Here are my specifications for the automatic planning :
I have an instance of Projeqtor which is hosted by you. The version on it is V7.4.4. I don't know how to fix this issue.
Thanks for your return
Best regards
Don't take into account my last message. I will read the document and will get back to you if I have the problem.
Hello,
So As I want to use an Administrative Project (type ADM) for my absences, it's normal that it's always mentioned "to plan" on my screen ?
I notice that the last planned and real end days will correspond to the last day of absence or whatever entered by a user.
Could you confirm ?
Best regards
it's normal that it's always mentioned "to plan" on my screen ?
Well, it's not "normal" but you can't avoid it.
Just don't care about it.