Hello,
I suppose the solution is very simple, but after 2 hours seraching I must admit I don't konow how to add an administrative project (in order to deal with holidays). :unsure: :unsure: :unsure:
AS AN ADMINISTRATOR :
I have created a project, type "Administrative", status "in progress" and add affectation to a project member (I know it not useful, but...)
AS THE PROJECT MEMBER :
When I log as the ressource (filter up left "All projects") the project doesn't appear in "Follow-up / Real work alocation" => where is the mistake ? How can I write down the days off if I can't see the administrative project ?
(for information, when I go to tools / Parameters / User parameters, the combo box do list my administrative project)
Thank you
(version 5.4.5)