[#7073]

Hello,
I need your help on the following issue:
A project member -call him Luke- leaves a project on Dec. 31 this year. He will be replaced by Rey, who is already working on the project, with a working load compatible with this replacement.
I have tried the replacement button on a dummy project, specifying that the "new" Rey starts working on January 1st, 2021. Luke is affected until the end of the year, but Rey also! Is there a means to force her affectation on Luke's tasks after Dec. 31st, while keeping her previous affectations? I would not like to modify all the tasks in the existing project.

Thanks in advance.


Bernard

 
Posté : 1 Déc PM 12:1212
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hi
Do not worry, the assignments will be changed automatically without having to change them manually. Please note that on project screen you will get two lines for the remaining resource on allocations that you are allowed to change anyway

You re welcome.


 
Posté : 1 Déc PM 13:1212