I have quite a few projects, but the planning always seems to only be able to be done by project. This makes it hard as I have to plan each project individually one project at a time. Is there anyway to have the program plan all projects at once?
When you run plannig calculation, in the pop-up, select no project :woohoo:
I try, but I get this message all the time
Max Projects to display exceeded
You must select a project
This means you have too many project to try and display in Gantt Chart (too big gantt chart may crash browser)
This may occur is you have sdmin rights (you see all projects)
You can try :
- Move the projects you want to replan together as sub-projects of same top project, then replan the top project
- Change your access profile (or create new user) to Project Leader, allocate to corresponding projects, replan all (this will include only allocated projects)
- Increase Max Projects to Display in Global Parameters.