Hi !
I have a question : when I use as soon as possible planning mode, planning calculation don't take care about validated start date. Is it an issue ?
Thanx for your answer.
Cédric
when I use as soon as possible planning mode, planning calculation don't take care about validated start date. Is it an issue ?
No it is not an issue, it is expected behavior.
Validated start and end dates are records for initial planning, on which you have committed.
If you want to fix start date you have to add fix milestone and add dependency to activity.
Thank you for your answer, I'll use Milestone !