Good afternoon,
i wish to know if it is possibile to make that activities in a status "eg: standby" are not considered when planning is calculated, to avoid to manually remove left work and re-enter i when we wish to restart to work to those tasks
Thks in advance
Stefano
Posté : 12 Mar PM 19:033
No, there is no suck behavior.
Posté : 13 Mar PM 17:033