Is there a possible way to see the baseline (requested dates) in the planning ? This would help to see quickly the tasks which have a delay.
Thank you.
Posté : 20/07/2016 6:39 pm
This is subject of Ticket #1654, planned on V5.6
But you can already see delayed tasks as they appear as red bars on Gantt view.
Just pay attention that baseline is "validated" dates, not "requested".