I have read two différents thinks in the help for order of calculation priority method.
first I read:
[list=1]
Second I read:
The calculations are performed task by task, according to the following organization:
1- WBS
2- The validated end date
3- Priorities of activities
4- Project priorities
5- Planning modes
6- Dependencies
So what is the order high priority calcultation
Hi,
Could you tell me where do you find this kind of informations, which links are they coming from ?
The good answer is the first sort.
I find it on th helping menu on the application
Thank you, but what about the second sort ?
could you please explain me the third point ...
Prioritized planning elements
modes of planification get an order of priorization beetween them.
Manual then regular then recurring then ASAP