Change duration in hours of a day

3 Posts
3 Users
0 Reactions
2,808 Views
(@belsebou72)
Posts: 9
Active Member
Topic starter
 
[#4160]

Hello,

I can't change the duration in hours of a day

tanks


 
Posted : 02 Mar 2017 16H39
ANOLL
(@krowry)
Posts: 131
Active Member
 

Hello ,

"unit for real work allocation" is on format "hours" . If you want to change the value of " nombers hours per days " you need to change the "unit for real work allocation" in days .


 
Posted : 02 Mar 2017 18H15
(@babynus)
Posts: 14952
Member Admin
 

But pay attention : if you change "number hours per days" and some real work exist, users may face weird display in real work allocation.
This is because work is always stored in days in ProjeQtOr. So input / display in hours is just convertion.

Imagine you set "number hours per days"=7
Then user enter 7 hours today. Projector store 1 day.
Then you set "number hours per days"=8
User returns to real work allocation and sees 8 hours for today (that's not what he entered 🙁 )


 
Posted : 02 Mar 2017 23H29