Hi,
In Client Quotations is planned date referring to the date until when the quotations should be prepared? If not, where should I set the date until that the quotation must be made?
Regards,
Zsolt
Posté : 20 Nov PM 19:1111
It was not designed this way.
It xis entended to store planned end date of work to execute
Possibly it could be called "planned delivery date"
But as ProjeQtOr may adapt to your process, you may enter planned end date of quotation task.
There is no other "planned end date" defined.