We are working in hour, not in days and contributor receiving this kind of mail :ressourcechargeXXXXXX Vincent17/06/202218/06/202219/06/202220/06/202221/06/202222/06/202223/06/20226,02 h0 h0 h7 h0,98 h0 h0 hbut he enter 6 on monday and 1 on 21 !(the 7 on 20/06 is an holiday so 7 !)How could i have an extract with 6 and 1 ?LR
Hi,
CSV Export has not possible indication for scale of work, so it is always returned in default projeqtor format, which is "in days"
Dear Babynus
For export in CSV i understand but i've got the issue in Projeqtor Alert mails ( see in attachments ) and info is hours converted to days and converted to hours ....
not possible to send the alert in hours cause screen is ok on projeqtor, taking data from the same field as enter inside imputation ?
Loic
I see.
There is a rounding issue.
Ticket #6268
Hello,
Today one contributor have an email alert with surprising time information ( double conversion hours to days to hours ... ),
ressource charge
XXXXXXX 22/09/2022 23/09/2022 24/09/2022 25/09/2022 26/09/2022 27/09/2022 28/09/2022
7,98 h 6,02 h 0 h 0 h 7,98 h 7,98 h 3,01 h
Your previous patch was working well on previous 10 version but it seems that it was not applied on 10.1.1
Thanks for your feedback
LR