Bonjour,
Vraiment bien et complet ce logiciel.
Par contre, quand je créer une réunion je ne retrouve pas le couts de cette réunion dans mon projet ?
Merci d'un réponse
@+
Fred


 
Posted : 19 Jan 2016 11H45
(@babynus)
Posts: 14952
Member Admin
 

Please post in english : http://www.projeqtor.org/fr/forum-fr/aide


 
Posted : 19 Jan 2016 13H49
(@babynus)
Posts: 14952
Member Admin
 

Cost is calculated for meeting exactly like for activities.
1) define cost for resource in resource screen : cost is defined for a given funntion, and you can select default function for resource
2) on meeting, add resource as attendee (participant) for some work (work is automatically proposed from meeting duration) and some function, that will select cost for resource
3) cost is automatically calculated for meeting, and taken into account on project costs.


 
Posted : 19 Jan 2016 13H56