Im looking for a way to show the diary and timesheet for all users of a project or team, or resource pool.
Right now it seems that the only way to check diary and timesheet for some members is to select each one of them (from the resource combobox) and see what they entered.
Is there a way to show this info grouped by resource somehow ?
Ideally i could show the timesheet grouped by project and resourceuser, and the diary also grouped by project and resource when using week view (or even month view).
Have you looked at the resource planning screen?
You can view resources in the same project and sort them by resource, team and/or organization.
Its empty.
Does this use activities ?
I mainly added tickets.
What data should be used in resource planning ?
Hi,
tickets are not plannable and will therefore not be visible or interpreted on a gantt chart. (Except on the global planning view as regards ProjeQtOr).
So effectively the planning by resource which uses the activities will not be useful to you to visualize the work.
A solution would be to link your tickets to a planning activity and/or use the synchronization on between ticket and activity.
Hy there.
Sorry i took a while for me to get back here but ive just been very busy.
So its not clear to me if its possible to achieve this.
So right now i dont see any way to show the info shown in the timesheet page, but for all the users of a project.
If i link a ticket to a "planning activity" and go to planning, i see the activity, but i cant see the ticketstasks and the hours worked.
Right now im thinking that the only way is to maybe extract this directly from the database.
So, sorry if im repeating myself, but what i would want is to see exactly what i see in the timesheet page, in the month view, per year and month.
The only change that page would need is the ability to show rows for all resources of a projectteam.
If i link a ticket to a "planning activity" and go to planning, i see the activity, but i cant see the ticketstasks and the hours worked.
And of course on the activity used to link the tickets, if you go to the steering section, you have a summary table of the linked tickets
and if you click on the eye you see the complete and clickable list of tickets linked to the activity with some information that might be useful to you
So, sorry if im repeating myself, but what i would want is to see exactly what i see in the timesheet page, in the month view, per year and month.The only change that page would need is the ability to show rows for all resources of a projectteam.
It is not planned that we develop the timesheet view with a yearly display, which would be, I think, not very readable or with horizontal scrolls of several seconds...
But, you can contact us via the contact form for any quotes on the requirements, specific to your use case, that you may have.
Otherwise, just by chance, have you looked in the reports to see if one of the 130 models we offer would not meet your needs?
So i think i found a report that has what i need.
Its "work monthly detailed by resource".
It has a filter on project team and resource.
Ideally this would have some other filter like milestones, and maybe ability to show the detailed report a week by week basis. But its ok for now.
Only one this i wish i could change to it. The activity column seems waaay to small (its width). It would be nice if i could resize it somehow.