Hi,
I would like to ask whether it is possible to filter the items such as project, task, action, ticket etc. by automatic calculated status (e.g. compare validated, requested, planned end date to its progress). The goal is to be able to quickly identify and sort out the tasks that are late/completed/future task for addressing the items with real vs plan differences. I included screenshot of the default column in MS Project for the auto-calculated status for your reference.
Thanks,
Rainbow
Hi,
On each for, you have advanced filtering filter, so you can build filters you need.
For instance on Activities : Validated end date <= today - 1 days (late activities)
Or sort on status, or whatever you want.
Idea added to ticket #2596 dealing with locale timezone of users