Hi all,
i'm working on 7.2.7 version and tried to fill a 1,5 day of duration. When i validated this input he changed it on 1 day (instead 1,5 day)
Can you help me please on this point
Thk,
Didier
Posté : 18 Mar PM 13:033
i'm working on 7.2.7 version
🙁
tried to fill a 1,5 day of duration
Duration is always in "open days", without decimals.
So smallest duration is 1 days (even for tasks planned for 1 hours)