Hi,
I have a project containing a fixed milestone (it's an external deadline). For planning a task which must be finished before this milestone I simply created a dependency (end - start) between the task and the milestone.After pressing the "Planning" button" the following Gant shows up:
Of course the milestone will be placed at its fixed date. The activity takes longer than the milestone since I assigned too much work to this task in order to meet the dependency. My question now is: Is there a way to receive a warning (while planning) that in this case the dependency cannot be hold. I know that the task appears in red if it has a validated end which is behind the planned date. However at the time of planning there are no validated dates yet. So is there a way to get warning while pressing the "planning" button or is there another mechanism?
Best regards,
Udo Eisenbarth
