Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hello,
I am evaluation Projeqtor for my company and it is really a fantastic tool!!
So far, I have been able to do almost exactly what I wanted.
I have a question though.
I would like to know if it is possible and how to create task that needs eg a Machine (physical resource) and a human to complete.
I have created a tool (say hammer) and a person say Joe. In order to complete a task "putting nails" I need both the hammer and Joe.
If Joe is unavailable on Friday, I can't use the hammer to work on the task that day.
Or if the hammer is used on another task by jane, Joe can't work...
Is there a way to do that?
Thanks,
RG
Hi,
To do what you describe is easy, and you're almost there :
- Create one resource for Hammer
- Create one resource for Joe
- Assign Hammer and Joe to same task (with same work)
- change planning mode of the task to "work together" :woohoo:
Run planning calculation... 😉