i created a project with some activities . Now when i go to the project, the PLANNED END DATE is giving me dates i did not put .The crazy thing is i cant change the dates.My starting dates are good, my end dates are good. The only problem is the PLANNED END DATE that i would like to change please. In the Attacment you will see the date 26/08/2044. Merci.
Planned dates are calculated from Work assigned, taking into account all the constraints (resource capacity, planning mode, priorities, dependencies, ...)
Hi,
I got same issue . They are two hours at list I'm trying to understand where the planned date has born in order to change it . No way until now.
I checked all Projects. Activities, Resource, Users ...
The solution is really nice but it's too complex to understand in all its behaviors .
Hello,
it is not complex, it is complete.
yes, It takes a little time (and money) to invest to understand how it is powerful and usefull.