How to get activity planned date calculated ?

3 Posts
2 Users
0 Reactions
2,845 Views
(@albeud)
Posts: 7
Active Member
Topic starter
 
[#4561]

Hello,
I try to find the answer by myself, using this forum or the demo project. But I still can't find the solution...
I'm creating an activity, and when I assign the workload to a ressource, I would expect to get starting and ending planned date to be calculated automatically.
Unfortunately, this is not the case (see attached picture). So I guess I'm doing something wrong...
I saw in many post that I needed to run a planning calculation, but I can't find this action, and when I search this in online help, I get no result.
So if someone could help...
Thx a lot !


 
Posted : 07 Aug 2017 16H54
(@babynus)
Posts: 14952
Member Admin
 

You must run planning calculation, using corresponding button (gears on planning screen)


 
Posted : 07 Aug 2017 19H08
(@albeud)
Posts: 7
Active Member
Topic starter
 

Thanks a lot.
It was so obvious that I didn't get it.... (I was searching in sub-sections of left panel...)


 
Posted : 07 Aug 2017 19H19