Hi,
I am learning how Projeqtor works. I have search within the forum without results. So, I hope not asking an already treated subject.
I have created a project and then, an activity. The first dates fr the activity were may 5th. However, the meeting has been postpone on may 7th.
Although I modified the dates in the activity control panel, the activity remain scheduled on may 5 in the Gantt.
I don't find how to modify easily without deleting the activity and creating a new one.
Could someone help ?
Thanks in advance.
Sterwen
"Le progrès ne vaut que quand il est partagé par tous" : merci à ceux qui partagent !
hi,
ProjeQtOr runs effort driven planning, based on Work.
Default planning mode is "as soon as possible" .
If you need fix date, use corresponding planning mode.