Hi,
I use 4.5.5 version
How to plan a activity of several week but which will take place several times ?
For exemple in my projet i have a "Formation" activity with 15 days, i want to plan this activity during the weeks 12 to 16/10, 26 to 30 and 23 to 27/11. Weeks or days do not follow each other.
How i make in the proiject for use the schedule and use the function of calculation of the schedule of the activities ?
Thank's a lot for your answer
In your exemple you just have 3 activities, that you can for instance plan as fixed duration.
You can if you please sum up these activities, just placing them under a top activity.