Hi,

I have a project that began in november 2017. Few tasks have been achieved in 2017 and wanted to model them.
I can setup a task with validated dates in the past, but it seems that the planified date are not set in the past. I am not able to indicate the task to begin in nov 2017. So the gantt is never OK, always beginning the 2018.

What do I miss ?


 
Posté : 14 Jan PM 19:011
(@babynus)
Posts: 14952
Membre Admin
 

When you run planning, set planning start date in the past.


 
Posté : 14 Jan PM 20:011