Forum

Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.

How to update the p...
 
Notifications
Clear all

How to update the progress of a task which does not have resource assigned

2 Posts
2 Users
0 Reactions
975 Views
(@kishorevenki)
Posts: 41
Active Member
Topic starter
 
[#9814]

Hi,
I have created a task say

  • Delivery of the materials 
    • Planning mode - ASAP
    • No resource assigned
    • Duration - 40d
    • Validated start - 31st March

But on 10th Aprilm I came to know that the materials will be available on 16th April. I dont want to change the duration at that point of time, because I want to compare the actuals with baseline dates. Further since there is no resource assigned, timesheet cannot be used to enter the actuals. 

Kindly advise. 
Regards,
Kishore


 
Posted : 16 Apr 2025 18H57
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

Hello,

Your question is how to update the progress of this activity. OK.
So my question is how do you do to follow the progress before this modification of date ?
In fact, it seems difficult to calculate a progress without data workload. Alternatively, you can continue to use a rule of three to personally assess the progress calculated over different timescales.
Perhaps I don't fully understand your concerns so my answer at this point is : The progress depends on your own calculation then written down into a textual area.
Otherwise, use the functionnality "BASELINE" to keep a photo of your project with this activity you can compare later with your current Gantt. 
Best regards


 
Posted : 17 Apr 2025 13H26
Share:

Scroll to Top