Hi Expert,

As we want to input any tasks/activities in planning under activity > detail >  "To do" list after WBS Indent level reaches level 4 (i.e. X.x.x.x.x in our case).
It means activities should be permitted to be entered only up to indent level 4 i.e. it should not be added any activity if it's WBS indent reaches up to X.x.x.x or should be alerted to the user. Is it possible in our tool?

I know it will affect many things, but it looks useful for all & If we can't restrict using any parameter available, it can be given only alert as per parameter defined for WBS indent level limit.

Please find attachment for better understanding.  
 


 
Posté : 23/08/2022 2:49 pm
(@babynus)
Posts: 14952
Membre Admin
 

It means activities should be permitted to be entered only up to indent level 4 i.e. it should not be added any activity if it's WBS indent reaches up to X.x.x.x or should be alerted to the user. Is it possible in our tool?

No, it's not possible


 
Posté : 23/08/2022 8:15 pm