Dear Babynus,
Thanks a lot for your last release and the test session in gantt planning function integrated inside.
Within this function, it would be nice to choose a parent activity or parent test session from a parent project for a sub-project.
Is it possible or already recorded in the tickets ?
For my job, on which I manage a lot of test activities from many sub-contractors, I have global test sessions for them and so on, this function would help me a lot.
Thank you in advance for your reply.
Nota : I see that other functions I need are already in your tickets (calendar for each ressources. I use your solution from now).
Luckydigit
Hi,
Test Session can have parent activity or parent Test Session.
But always within same Project.
It is mantadory to respect WBS structure : an item cannot be sumultaneously at different places in the structure.
But what you can do is copy a test session into another project.