Ligne "charge" not visible for profile "external project manager"

8 Posts
3 Users
0 Reactions
6,044 Views
 Phil
(@phil-bzh)
Posts: 27
Active Member
Topic starter
 
[#3824]

Hello,
What can I do to make visible the line "charge" for the profile "external project manager" ?
Thank you.

Bonjour,
Comment faire pour que les ressources associées au profil "chef de projet externe" voient la ligne "charge" dans les assignations ? Voir le assigné, le réel, etc. mais sans le modifier.
Merci.


 
Posted : 14 Nov 2016 3H48
(@babynus)
Posts: 14952
Member Admin
 

Update rights in Specific Access Rights


 
Posted : 14 Nov 2016 10H02
 Phil
(@phil-bzh)
Posts: 27
Active Member
Topic starter
 

Hello babynus,
Thank you for your answer.

I did go to Parameters / Access rights / Specific access, and I've chosen work visibility = all visible and view assignments = yes

And in the block "Progress" of the actvities there is still no line "work :" between line "duration :" and line "progress :"

Maybe I must modify another value ?

Phil.


 
Posted : 14 Nov 2016 21H50
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi Phil,

not clear if I understood you right.

In the line 'progress' there will be no line with work. It shows percentage of progress.
Work is displayed in the line 'work'.

May be a screenshot enlightens your issue.

Regards,
Klaus


 
Posted : 15 Nov 2016 9H07
 Phil
(@phil-bzh)
Posts: 27
Active Member
Topic starter
 

Hello
My concern is the line "work :", not the line "progress :" => better with an image (see attached) 🙂
On the right with profile Admin : the line work is visible 🙂
On the left with profile "External project manager" : the line work is not visible 🙁
Which right should I add in order to add visibility on the line "work :" (just visibility, not the right to change) for profile "External project manager" ?
Thank you !

(I changed the title : the english word for "charge" is "work")


 
Posted : 16 Nov 2016 0H03
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi Phil,

may I suggest to do following: see values in Access rights - Access to data (project related). For External team member should set adequate rights and it should work.

Regards,
Klaus


 
Posted : 16 Nov 2016 13H10
 Phil
(@phil-bzh)
Posts: 27
Active Member
Topic starter
 

Hello,
Thank you for your answer.
But which right (which line) must I modify in the column "External project manager" ? I have modified many, but still no line "work :" appearing...
Phil.


 
Posted : 16 Nov 2016 14H47
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi Phil,

below the standard access modes:

Change here, where the arrow ends.

Regards,
Klaus


 