Is it possible to change many activities at once?
I have created about 200 activities via copy and each one contains "validated dates". I want to delete them.
Can I do this somehow by changing the measures, or do I have to do each activity manually?
HI,
Yes you can.
use the buttom multiple update on detail area of activities screen ( icone = double floppy disks)
Regards
Well, greeat .... but i can not change it to "empty date"
You are right. A date is compulsory. Empty date should be allowed.
Recorded as ticket #4233#
so it's manual D:
Hi, could you please post a screen shot or a video where is this button?
It would be nice to mass edit several records at once in any view. My typical use case is change affectation of activities in the planning view.
affectation of activities in the planning view
This is call Assignment.
Search for this in the menu search area.