Hello!
If I create this report as admin, I get all active projects/activities of a resource including the administrative project for the holidays.
If I do the same as project leader or project member the holidays project is missing. It would be very useful to see also this days.
Is this a bug or what am I doing wrong?
Best regards
Thomas
In fact, administractive projects are displayed only if Project Leader is assigned to administrative project, to get visibility on it.
But you're right, on Monthly planning report or availability reports, administrative proejcts should always be taken into account.
Ticket #2022 recorded.