Order vs Planned Work for T&M project

2 Posts
2 Utilisateurs
0 Reactions
2,780 Vu
(@ade)
Posts: 45
Active Member
Début du sujet
 
[#4821]

Hi,

The feature to bill the T&M project is available based on a resource.

Do you have a feature to order T&M effort on a resource? The objective is to declare an order before starting the project : like a baselinework (an order) for the customer.

Example :
° declare a T&M project
* declare an activity
* declare resource
* baseline project
* evaluate the baseline work/cost
* make a T&M order based on resource cost/work

Thx for your answer


 
Posté : 6 Déc AM 10:1212
(@babynus)
Posts: 14952
Membre Admin
 

No.
The order should come become execution of work, so cannot depend on real work.


 