Hi,

I used projectOR for several years for tracking bugs or following work allocation but never tried to use the planification module up to now.

I was surprised by several aspects - may be I totally missed the point... :

  • Is there any way to visually distinguish between Activities on track and Activities on overrun (whatever the overrun origin : remaining work reevaluation or real work allocation exceeding the anticipated effort ? Everything stay green :dry: ... on the Gantt diagram.
  • when a developer updates a remaining work, he or she can silently impact the whole planning. Is there a way for the project planner to be notified of the shift ? And its origin ?
  • Is there any validation possible to prevent remaining work changes without notice ? Including a what-will-happen developer curious about the impact of tuning this "weird" field just to see its effect.. :whistle: .

Thanks in advance


 
Posted : 18 Nov 2014 20H36
(@babynus)
Posts: 14952
Member Admin
 

Is there any way to visually distinguish between Activities on track and Activities on overrun (whatever the overrun origin : remaining work reevaluation or real work allocation exceeding the anticipated effort ? Everything stay green :dry: ... on the Gantt diagram.

On Gantt Diagram, you have mostly view over planning dates. Tasks become red when planned end date is over validated end date.
To have overview about work overrun, just have a look at report Work / Work synthesis per activity.

when a developer updates a remaining work, he or she can silently impact the whole planning. Is there a way for the project planner to be notified of the shift ? And its origin ?

Yes, alerts can be send when planned work (real+left) is over validated or over planned work.
Have a look at indicators.

Is there any validation possible to prevent remaining work changes without notice ? Including a what-will-happen developer curious about the impact of tuning this "weird" field just to see its effect.. :whistle: .

You can define alerts (as described above) of have a validation process of real work allocation.
There is possibility to submit and validate weekly real work, so that project leader has an overview about global work on project.


 
Posted : 18 Nov 2014 21H47
 hle
(@hle)
Posts: 9
Active Member
Topic starter
 

Thank you for all those replies.

Is there any way to visually distinguish between Activities on track and Activities on overrun (whatever the overrun origin : remaining work reevaluation or real work allocation exceeding the anticipated effort ? Everything stay green :dry: ... on the Gantt diagram.

On Gantt Diagram, you have mostly view over planning dates. Tasks become red when planned end date is over validated end date.

Is a four stage approach possible :

  1. activity definition (and dependencies)
  2. resource allocation (effort)
  3. using the gantt views, computation of the planning
  4. validated start and end dates automatic setting ? i.e. setting validated dates = planned dates globally, without manually entering each date for each activity ?

There is possibility to submit and validate weekly real work, so that project leader has an overview about global work on
project.

When entering real work allocation, I wonder about the differences between submit work and validate work buttons and how they affect planning computation ? No impact for instance until the project manager has validated his/her team work allocation entries ?

THX 🙂


 
Posted : 19 Nov 2014 13H36
(@babynus)
Posts: 14952
Member Admin
 

Is a four stage approach possible :
activity definition (and dependencies)
resource allocation (effort)
using the gantt views, computation of the planning
validated start and end dates automatic setting ? i.e. setting validated dates = planned dates globally, without manually entering each date for each activity ?

Yes, this is exactly in ProjeQtOr scope.
NB : definition of dependencies can be eased in Gantt view (drag & drop mode)
NB : to save validated dates, use correspondng button in plannong screen (the one woth the check, beside print button)

When entering real work allocation, I wonder about the differences between submit work and validate work buttons and how they affect planning computation ? No impact for instance until the project manager has validated his/her team work allocation entries ?

Submit button appears only if connected user is the current resource. It is for the resource to submit the weekly work.
The validate button apperas only for project leader (or other profile habilitate to...) to validate the submitted work.
Both have no effect on planning calculation : it only locks real work for the corresponding week.


 
Posted : 19 Nov 2014 19H09
 hle
(@hle)
Posts: 9
Active Member
Topic starter
 

Thanks a lot for your assistance, from St Martin du Touch 🙂 We seem to be neighbours.
French not allowed in the forum :silly: ?


 
Posted : 19 Nov 2014 20H17
(@babynus)
Posts: 14952
Member Admin
 

Hi neighbours,

Fly Aircrafts at St Matin ? :whistle:

English is mandatory in the forum so that most community users can benefit of questions and answers 🙂
Frensh is available only through professionnal support service :whistle:


 
Posted : 19 Nov 2014 20H55
 hle
(@hle)
Posts: 9
Active Member
Topic starter
 

Fly Aircrafts at St Matin ? :whistle:

No, flying higher (low earth orbit).

French is available only through professionnal support service :whistle:

I've made a note of it.
Free english training at the instant 🙂


 
Posted : 19 Nov 2014 21H57
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi Hie,

hint: for translations is google my best friend; not for English, but for all the other nice languages.

Klaus


 
Posted : 20 Nov 2014 16H06
 hle
(@hle)
Posts: 9
Active Member
Topic starter
 

For my part, I really appreciate Linguee ( http://www.linguee.com) in particular for idiomatic expressions (full text comparison of professionaly translated documents).


 
Posted : 24 Nov 2014 13H10
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Yes, you are right, linguee is good as well.


 
Posted : 24 Nov 2014 15H43