Hello everyone.

I think i have an issue with plannification.
One of my project is finish (all activity and the project itself is done) and there is no more left work.
However when i want to see work plannification i can see that one of my ressource has always planned ressource on this project.

Can you help me please.

Have a good day 🙂


 
Posted : 20 Sep 2016 12H40
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

Just recalculate planning for project, it will refresh planned work.

Planned work is removed only if resource enter real work exactly as planned.
In other cases, some planned work mayu remain, and only recalculation of planning is able to refresh planned work.


 
Posted : 20 Sep 2016 13H09
(@jonathan02500)
Posts: 21
Active Member
Topic starter
 

Ok, how can i do this operation please


 
Posted : 20 Sep 2016 13H17
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

In planning view, click on the corresponding button.


 
Posted : 20 Sep 2016 14H08