Hello,

How to force the planned start date to be calculed ? In fact, in my project I have a planned start date for a parent activity : 03/04/2014 while all validated start date are > 05/05/2014.

I calculated several times the planning via the button without succed.

The planned start date should be 05/05/2014

Thanks


 
Posted : 11 May 2014 12H41
(@babynus)
Posts: 14952
Member Admin
 

Do you have some work defined for your tasks ?
If not, what is the planning mode )
For defaut planning mode (as soon as possible) you need to have work defoined to get some result.
Otherwise, you need to change planning mode (fixed duration) to get things calculated


 
Posted : 11 May 2014 14H42
NOUR EL DINE
(@hnoureldine)
Posts: 16
Active Member
Topic starter
 

hello,

it's solved now by affecting ressources to the parent activities.


 