In Progress section (project panel) I want to manage my project, upon its Planned Date and Real Date.
I Dont' want to let the System calculate the validated Date automatically according to the entree Day Date, unless I enter it, manually. I Want to have full control of the validated Dated.
I Love ProjeQtOr , but How to setup the calculation of the Project's Date(s), because there is too much date(s) to manage in ProjeQtOr. !!!
we are missed up and mixed up with all the Dates !!
THX mate.
RTFM !
Validated = initial baseline (not calculated, manually entered or automatically copy from planned through planning validation button)
Planned = Calculated from wontrintes you gave (work, dependencies, planning mode)
Real = from Real work Allocation (first entered day = start, last entered day when no left work = end)
Requested = requested by customer (not often used)
Luckily we hide "latest" which are calculted to define critical path.
Thanks for the reply,
but I still lost in the explanation you gave. Can You Just say in French ?
Merci.
Sorry, help in french is provided only to subscribers to Support Service.
Read the user manual.