Hi,
I have an activity planned on 18th March (half day). The next activity (linked to previous one) is still on 18th March for half day also, but done by another responsible. I do not understand why the second activity is planified on 19th March even if both activities can be done the same day, ie 18th March.

Please find screenshot attached

Thanks for your help.


 
Posted : 01 Mar 2019 13H52
(@alain-fourastie)
Posts: 366
Member Moderator
 

ello

Please check it on global paramters as follow, change yes by no ( can start the same day)

Regards


 