Hello,
I'd like to know if there is a report or view that allows you to compare the planned with the real planning without looking each activity?
 

Thank you 


 
Posté : 14 Jan PM 17:011
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hello,

Go to the dedicated project screen that consolidates all activities, or move the splitter on gantt chart beetween lines and chart, or go to reports to look for the wished report.
Be careful  and please read the friendly manuel  ! Planned is calculated by the application. the real is the first and the last dates of work done, the wished planning is given on validated dates that you define yourself, you have just to compare yours and the calculated ones.


 
Posté : 14 Jan PM 17:011
(@loline77)
Posts: 6
Active Member
Début du sujet
 

Thank's for your answer but I made a mistake in my question I want to see yhe difference with asked and real.


 
Posté : 14 Jan PM 18:011
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Same answer, please explain to us.


 
Posté : 14 Jan PM 18:011
(@loline77)
Posts: 6
Active Member
Début du sujet
 

Sorry, I don't speak english very well, I hope my picture can explain better than me.
I'd like to see the late in the project.


 
Posté : 15 Jan AM 11:011
(@babynus)
Posts: 14952
Membre Admin
 

Requested dates are just informative.
As of today, not report or display uses these data for some comparison


 
Posté : 15 Jan PM 20:011