Hello, Babynus!
Could You tell what smallest time could be assigned for activity? I have discovered, when time is less than 0.1 hour for activity, Projeqtor calculated wrong, it wasn't able to set dates.
Could I have ability to plan these small activity?
Thank You in advance! 🙂
Hi DEngine,
what's rational behind your small activity? Might be a milestone will manage your target as well.
Regards,
Klaus
If you plan very small activities, maybe you should change unit for work (in global parameters) to set it ti hours.
Then you can manage fractions of hours (0,1 h).
But is it really reasonable to manage such small tasks ? :ohmy:
Maybe you'll spend more time managing them than treating them :silly:
IMO, tasks should not be spit to less that 1 day activitiy, and best size is about 5-10 days...