Notifications
Retirer tout
Ask questions
3
Posts
2
Utilisateurs
0
Reactions
2,124
Vu
Début du sujet
Is it normal that the priority on a planning of a project is not passed on to the subproject?
If I put a priority to 850 on project 1, and I do not touch the priorities of subprojects 1.1, 1.2, etc ...
During a planning calculation, the project 1 retreats well in time, but not the subprojects 1.1, 1.2, etc ...
I am obliged to apply the priority 850 to the project as well as all sub projects ... Is this normal?
Posté : 11 Avr PM 17:044
Yes, priority is not inherited
Posté : 12 Avr AM 02:044
Début du sujet
pity, it would simplify the planning calculation for us
Posté : 12 Avr AM 11:044