Is it normal that the priority on a planning of a project is not passed on to the subproject?

If I put a priority to 850 on project 1, and I do not touch the priorities of subprojects 1.1, 1.2, etc ...
During a planning calculation, the project 1 retreats well in time, but not the subprojects 1.1, 1.2, etc ...

I am obliged to apply the priority 850 to the project as well as all sub projects ... Is this normal?


 
Posté : 11 Avr PM 17:044
(@babynus)
Posts: 14952
Membre Admin
 

Yes, priority is not inherited


 
Posté : 12 Avr AM 02:044
(@durou-c)
Posts: 468
Contributor
Début du sujet
 

pity, it would simplify the planning calculation for us


 