Problem to update the planned start date of an activity

2 Posts
2 Users
0 Reactions
2,979 Views
THIEME Bruno
(@omnitservices)
Posts: 3
Active Member
Topic starter
 
[#3099]

Hi everybody,

While I was trying to put some dependancies between tasks, the system automatically updated the start planned date of an activity.
This data is not correct and I would like to change this one to the correct value.
Can someone tell me how to do it ?

Thanks in advance


 
Posted : 25 Feb 2016 12H28
(@richard-pare)
Posts: 165
Active Member
 

You can't change planned values directly.

Planned start date can come from validated start date or requested start date.
Mainly, come from planning calculation (planned work assigned).

Often, the problem is a misunderstanding of ProjeQtOr.

Can you send more detail about your case?


 
Posted : 25 Feb 2016 16H51