Iaurkano
(@iaurkano)
Posts: 104
Active Member
Topic starter
 
[#3100]

hi babynus,

Is it possible to put a project in stand-by mode. The need is to free all ressource assigned on this project, when the project is intand by mode.
in fact, sometimes, we work on project plan, ressource assignement, etc. , and a change of priority happends. so the project is suspended, until an unknown date. it will done after but we dont kown when . In this case it should be great to put project in stand-by mode, to keep the plan, but it's needed that this project does not impact ressource avaibility for other one's.

i don't known if i'm clear, i hope, i'm .....

Thank's a lot and

Thank's for your work.


 
Posted : 25 Feb 2016 12H40
(@richard-pare)
Posts: 165
Active Member
 

You can close project affectation for these resources.
Check box "Close" in "affectation" dialog box.
You can change project affectation period.
You can fix project planning.


 
Posted : 25 Feb 2016 16H36
(@babynus)
Posts: 14952
Member Admin
 

beszt way is to plan the project with plan start date very far inthe future (01/01/2050) for instance.
then check the fix planning ckeckbox and put in a specifc status.


 
Posted : 26 Feb 2016 0H01
Iaurkano
(@iaurkano)
Posts: 104
Active Member
Topic starter
 

Ok i will try.

thank's for your help.


 
Posted : 26 Feb 2016 11H02