Real work allocation issue TASKS

2 Posts
2 Users
0 Reactions
2,790 Views
(@karl-binet)
Posts: 128
Active Member
Topic starter
 
[#4817]

HI,

I have about 15 tasks asign to specific users. Let's say, user, Bob and Bobby.

If I open real time allocation for those 2 users, no probem, i see all the 15 tasks.

But, in real time allocation, if a select another user, let's say, Rose, all the 15 tasks get's assign to Rose. even if in each tasks, the assignment was Bob and Bobby,. Now if look at all the 15 tasks, Rose is now assign to those tasks

And so on, if in real time allocation, if a select anothers user, this user get's assigned to all the 15 tasks.

I have about an hundred tasks, but only those 15 are assigned automaticly.

Anyone can help with this issue.

Regards
Karl


 
Posted : 05 Dec 2017 18H16
(@babynus)
Posts: 14952
Member Admin
 

Your project type is "Administrative".
This is a very specific type.
Just select any other operational type (not Template, not Administrative)


 
Posted : 05 Dec 2017 21H53