Hi
In Real work allocation screen, Want to view Activities on Project wise. While selecting the project from drop, it is not functioning. Is their any way of getting this? or any settings need to be done.
Regards,
Saran
On real work allocaton, list of items is always "all available items", whatever the project selected.
It is designed this way to be sure to propose all possible allocations, and to show all real works (possibly already entered so that total is exactly total for the week, for all projects)
Thanks for your valuable reply babynus.
Page loading time takes more while we save Activity entry. Can this be implemented? It would be useful if it was provided with project wise activity entries. Please do needful.
Thanks.